Albania: Hydropower Privatization

PPP Briefs
Published: 2013
Last Updated: 13 Nov 2024

In September 2008, the government signed a 35-year concession with Verbund (Austria’s largest electricity company) to build and operate a new hydropower plant. Over a threeyear period, the project mobilized $262 million in private investment, increased Albania’s power generation capacity by 53 megawatts, and delivered improved services for 170,000 people. Construction of the plant began in January 2010 and became fully operational in March 2013.

Document TypeBriefs
LanguageEnglish
SectorHydropower, Energy, Water, Generation, Electricity, Renewable energy, Power
File TypePDF
ContributorWorld Bank Group (WBG)
Country
RegionEurope & Central Asia

Translations