|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Renegotiation and Amendments to PPP ContractsA crucial activity of the Contract Management team is to try to prevent disputes and if they arise, the ways to minimize serious impacts on the project/parties to the contract. Renegotiations are becoming more common features of public-private partnerships (PPPs) and Governments need to recognize this and limit the risks involved. The increase in renegotiations has been noted in an increasing number of reports and if it does become increasingly common and changes become significant it can make all previous project preparation and bidding meaningless. This is especially so if the winning bidder has intentionally prepared the bid with renegotiation in mind. Renegotiation is a double edged sword for public authorities. A major reference study on renegotiation is referenced below; Basic DisadvantagesA particular case occurs when the private party initially overestimates the potential demand and later attempts to renegotiate the agreement, so that the public party is obliged to bear the costs related to demand risk to avoid the complete failure of the PPP. In those circumstances, the private party can bargain favorable contract terms that would have never been obtained under competitive conditions. The absence of other competitors during early renegotiation phases significantly weakens the public party's bargaining position, and in turn reduces the chances to achieve real value for money from the PPP agreement at stake. Renegotiation is thus generally regarded as undesirable because:
Occasional Advantages
It is of utmost importance to distinguish between contractually scheduled renegotiations and (early) unforeseen renegotiations that are initiated at the request of the private party. For example, early renegotiation sometimes takes place when the private operator realizes, during the operational phase, that it is not able to abide to the terms of the contract and/or needs more financing. Reasons and outcomes of renegotiationRenegotiations occur for a number of reasons including;
Source; Guasch 2004 Common mistakes which can lead to renegotiationGuasch lists a number of common mistakes, many of which can be characterized as poor design and too hurried implementation lead to subsequent financial disaster
Outcomes of RenegotiationOn average the terms of the contract improved for the operator/investors.
Who initiates the renegotiation process?In addressing the issue of renegotiation, it must be remembered that over 25-30 years there will likely be continuous 'fine tuning'. In this respect, renegotiation may be initiated by both the public and private sectors for the following reasons:
Lessons learned in contract renegotiationA report by Dr S. Ping Ho provides some insights into what can go wrong with concessions and that lead to the need for renegotiations. His report goes into depth on the Taiwan High Speed Rail project which opened in 2007 at a cost of over USD 18 billion. Within his analysis of many of the problems (mainly financial) that occurred, his report showed that of the two bidders, one provided a bid that in hindsight was too optimistic and that the government with its limited experience of PPP could not easily evaluate and which did not call on experienced advisors. Also for such a mega project, the government stated a number of times that the project would not be allowed to fail. Further, the project sponsors were mainly contractors rather than a consortium of developers who he believes concentrate on short-term contract profits rather than longer term operational returns. According to Dr. Ping, the lessons learned from the perspectives of his work include taking extreme care with PPP projects that;
Gausch considers a different set of recommendations but ones which are also very valid. These include;
Although in practice there are many guidelines for various PPP schemes in countries such as UK, these guidelines cannot be universal to every country in the world. Guidelines and policies need to be reexamined to fit the specific environment of a country according to certain logic. Make certain that any proposed amendments and renegotiations are subject to scrutiny, both within relevant government departments and by the public in general. The reference from South Africa notes the Systems Act of 2003 obliges a municipality to inform and consult on proposed amendments to PPP contracts. Extensions of the 2003 Act and detailed regulation in 2005 go much further in terms of consultation. Chile has attempted to go further by placing prohibitions on any changes that alter the financial balance of a contract. Amendments must be consistent with the PPP rules and regulations of the government. In conclusion, while experience and lessons learned from various countries are useful each country has its own specific experience and needs to consider when framing contracts. However, considering where a contract may go wrong is a good start when considering whether a contract is a candidate for potential future renegotiation. Other Contract AmendmentsOver the course of say 30 years there will be a continuous need for amendments to PPP contracts. This is normal. Many of these requested changes will be for mutual benefit of both partners. Refinancing after the project is constructed is becoming more frequent as once the construction risk is passed, and a project has opened, cheaper financing is often available. As with all requested changes, such refinancing negotiations should be as transparent as possible (as the situation allows) and the public sector should carefully balance all short and long-term impacts of change and try to obtain the best deal for the 'public' including reduction in tolls say for some targeted users. Any requested changes that are more than just minor changes should be considered by the contracting authority with input from advisors-legal and financial at least. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Last updated march 2009 |