|
|||||||||||||||||||||||||||
N4 Toll Road from South Africa to Mozambique
BackgroundThe rehabilitation of the N4 toll road forms part of the Maputo Development Corridor (MDC) project, between Johannesburg and Maputo, which also includes other modes of transport. Projects such as the MDC are seen in a larger context of a Spatial Development Initiative (SDI) by the South African government to promote development where export-oriented economic potential exists and with the assistance of the private sector.
Project Overview and DescriptionExtent of the toll roadInitially the project involved the upgrading and rehabilitation of 390km of existing road between Balmoral (20km west of Witbank) and Moamba (proximity of RSA/Mozambique border) and a further 50km long road between Moamba and Maputo. The project was later extended to include the N4 road sections between Witbank and Pretoria, a total of 630km. The road is partly 4-lane separated carriageways and partly 2-lanes with widening to accommodate large hauling vehicles. A one-stop border facility was developed at Komatiport/ Ressano Garcia in order to reduce cross-border bottlenecks between the two countries.
Duration and features of the concessionThe original agreement stipulated a 30 year concession period beginning in 1997. This period was maintained although in 2004 the contract was amended to extend the concessionaire's responsibility over the N4 road section between Witbank and Pretoria. The concessionaire now manages 630km of toll road, the majority of which is in South Africa and only about 50km in Mozambique. The cost of the initial contract was about 3 billion ZAR (South African Rand) - about 660 million USD in 1996 value over 30 years of which 1.5 billion Rand to be allocated in the first three and a half years.
The concession was awarded to the Trans African Concessions (TRAC) consortium. TRAC is responsible for the financing, design, construction, rehabilitation, operation and maintenance of the toll road. Financing for the project was split between 20% equity* and 80% debt. The governments of South Africa and Mozambique jointly and severely guarantee the debt of TRAC and to a certain extent the equity. The concession contract was signed with South African National Roads Agency (SANRAL) and the Mozambique Roads Agency (ANE) and ends in 2027, after which the road reverts back to the governments. For toll pricing purposes, four types of vehicles were considered (light, medium heavy, large heavy and extra heavy). Tolls are collected at six main line toll plazas and at two ramp plazas. However, only two toll plazas are located in Mozambique, implying that the project is by and large supported by toll revenues collected along the South African road stretches and that South African road users subsidise Mozambican users of the entire toll road. The concession was initially based on 0.20 Rand per km for a light vehicle and 0.50 Rand/km for heavy vehicles. Nonetheless, a discount system was introduced for commuters and local users. Since then toll rates have increased but the agreement stipulates that toll tariffs can only be increased annually in line with consumer prices. In practice, increases varied between South Africa and Mozambique, due to the exchange rate fluctuation between the South African Rand and the Mozambique Metical.Experience during various phases of the project to dateTraffic
Traffic volumes, which greatly depend on the trade and economic growth in South Africa and Mozambique, were less than the financers expected, but the concessionaires felt that the traffic growth is acceptable at rates between 5% and 7% per annum*. Issue of overloadingAlthough one of the major concerns of the concessionaire was the potential damage caused by overloading, the concession agreement did not specify regulations of truck loads. In order to overcome this problem, the concessionaire began assisting both governments in establishing axle load control measures. The project which is operational since 2002 consists of a set of six traffic control centres, adequately equipped with measuring equipment to weigh axle loads. These are complemented by mobile units that are dispatched to pre-defined lay-bye areas in the surrounding, where weigh bridges are installed and by weigh-in-motion equipment at certain points, which serve to identify possible overloaded trucks. Since 2007, a sophisticated overload control center operates east of Pretoria on 24-hour basis / 7-days a week, enabling vehicle testing and electronic tagging facilities. Between 2001 and 2004, it was noticed that overloaded vehicles fell from 23% to 9%. When a truck is found to be overloaded, it is placed in a holding yard where the load needs to be rectified, for example, either by redistributing the load more evenly over the axles or by downloading part of the load to be carried by another vehicle to be dispatched by the owner. Conclusions and lessons learnedThis particular PPP project is an example of a successful implementation of a toll road project which involves the cooperation of two neighbouring countries of southern Africa. The implementation of the project stemmed out of the political will of the two countries to build cross-border economic relations after years of unfavourable political conditions in both countries that hampered such relationships. This project came into being in spite of the imbalance between the two partners South Africa and Mozambique, regarding various aspects related to such a project. For example, the economy of South Africa is much stronger compared to that of Mozambique, most of the route is across South African territory, and most fees were likely to be contributed by road users along the South African sections of the road. The risk associated with the financing of the project was borne entirely by the TRAC consortium (no government subsides were allocated), although the two governments guarantee the debt. The entire toll road was rehabilitated and reconstructed to appropriate standards, including both dual and single carriageway road sections. This is believed to be in line with forecast traffic flows. Although the details relating to the setting-up and implementation of the PPP per se constitutes the main reasons for its success, other parameters related to the general context and environment of the project are also believed to contribute to these results. Among such parameters one could mention the following:
Among the problems encountered with the implementation of this project:
Some criticism levelled by the general public to the South African government regarding the massive investment in such a transport project included the fact that the project is likely to benefit big business and not much the poor. The governments of both countries indicated that mega projects such as Mozal Aluminum smelter near Maputo or the Pende gas extraction project are likely to benefit the economies of both countries and that in return is going to benefit the citizens. |
|||||||||||||||||||||||||||
Last updated march 2009 |